COMING SOON FEBRUARY 2021 – Library House

We’re excited to announce our new supported living development in Bestwood, Nottingham.

Library House is made up of eight self-contained flats over two floors. These new, purpose-built flats are perfect for people with acquired brain injuries, physical disabilities and learning difficulties. Each one-bedroom apartment has a modern kitchen-diner, living room and bathroom and there is on-site park, assistive technology and 24/7 on-site support available.

Designed for people looking to increase their independence, we will work with you to create a person-centred support plan enabling you to choose the type and level of support you envisage.

Development update – week commencing 14th December

This week we have screeded all the shower floors, continued with electric works on the ground floor and the heritage windows have been returned and fitted. Plus, the communal front door has been fitted and the ground floor has had the first mist coat!

Development update – week commencing 7th December

The lift installation is now complete and all ground floor bathrooms have now been boxed in and ply fitted to walls. We’ve also been installing the gas service pipe around the building.

Development update – week commencing 30th November

Following on from the previous week, we’ve continuing to plasterboard throughout and fitting the electrics on the first floor. The lift installation is also underway – perfect for accessibility!

Development update – week commencing 23rd November

At this point of the development, we’re really focusing on the workings of the house. This includes installing and testing the ground floor and first floor waste pipes, cleaning the lift shaft and adding the concrete floor.

Development update – week commencing 16th November

This week we dropped the scaffold, boarded the ceilings on the first floor and continued to plasterboard the ground floor.

Development update – week commencing 9th November

It’s all starting to come together! This week we’ve fitted the first-floor windows and the rainwater goods – a good job considering the weather we are experiencing! We also completed the dormer clad and screed to the first floor.

Development update – week commencing 2nd November

With the roof tiling now complete and the crash decking removed, we have now fitted the stairs and continued to work on the superstructure of the house.

Development update – week commencing 23rd October

It’s been a busy week this week as we are focusing on the all-important roof! This includes installing the flat roof timbers and completing the roof structure.

Development update – week commencing 16th October

As a brand-new development, the build is already progressing well. This means that the brickwork and blockwork is now complete, as well as the ground floor windows, the beginning of the plumbing and electrics and much more!